9.16.4. Participatory workshops in 5 selected areas
Summary table of the activity
Commitment, initiative and activity
Start
Fin
State
9. Observatory on Open Government
9.16. Public participation in the management of the NATURA 2000 NETWORK
9.16.4. Holding of 10 participation workshops for the application of governance models in 5 areas selected according to the criteria set out in the Natura 2000 Marine Network Governance Strategy
01/01/2022
12/31/2023
Finished
State of implementation
There has been a delay in the finalisation of the Governance Strategy involving a delay in the implementation of pilot projects for the implementation of the Strategy and associated participation workshops. Work is underway to implement the Marina Alta project. The remaining pilot projects have not yet been defined.