Axis Transparency. 3.5: Development Regulation of the Transparency Act
Objective
Development of Law 19/2013, of 9 November, on transparency, access to public information and good governance with the participation of interested agents during the public consultation period and the hearing procedure.
1. Prior public consultation (general lines of the Regulation)
Jun-17
Sep-17
Prior public consultation of the Project of Royal Decree of development of Law 19/2013 of Transparency has been carried out. All the information is in this link.
2. Writing of draft regulations and draft of MAIN.
This activity is complementary to the previous one. The objective was to assess, in collaboration with other bodies, citizens’ contributions and draft a draft with which to work with all stakeholders. A preliminary consultation with the bodies of the Ministry of Finance and Public Service began in November 2017. You can consult the detail in the text of the published report (pages 37 and 38).
4. Audience processing and public information.
may-18
may-18
The public information process took place from May 3 to 31, 2018. We received 37 contributions, which are being valued.
On 30 May 2018, members of the Forum were invited to attend a meeting at which DG Public Governance reported on the status of the project and its content. Informative note
The latest version of the project, 28/02/2019, was submitted to a new public information deadline .Thirty submissions were received.
5. Report on coordination and regulatory quality
may-18
July-18
The report of the Office of Coordination and Regulatory Quality was received on 29/10/2018.
6. Reports of other departments and bodies
may-18
sep-18
Reports have been solidified to other ministries, to the Spanish Data Protection Agency and to the Council of Transparency and Good Governance.
09/30/2018: received report from 7 Ministries and the Spanish Data Protection Agency.
12/31/2018: received a report from 12 ministries, the Spanish Data Protection Agency and the Council for Transparency and Good Governance.
The report has also been received from the Ministries of Culture and Sport, Defense and the Ministry of Finance, as well as reports from the Spanish Data Protection Agency and the Council for Transparency and Good Governance.
7. Report of Public Administrations
sep-18
OCT-18
03/31/2019: The project was submitted for the report of the Autonomous Communities and Cities and the FEMP, and 15 reports were received.
8. Report of the General Technical Secretariat
nov-18
nov-18
06/30/2019: received report from the General Technical Secretariat, dated 04-04-19.
9. Opinion of the Council of State
dic-18
Feb-19
06/30/2019: Sent to the Council of State for an opinion
10. General Commission of Secretaries of State and Assistant Secretaries
mar-19
mar-19
11. Elevation to the Council of Ministers.
Apr -19
Apr -19
(*) Possible states of the activity:
Futura (activity scheduled to start after 30/06/2019).
Partially executed.
Completed (activity completed within the deadline set in the Plan).
Terminated with delay (activity terminated outside the deadline set in the Plan).